Nancy

Turnkey including the following services:
In order to mount the can line it was necessary to prepare a complex platform unit and to install it. Due to cost reasons 80% of the materials were used parts. The cost saving thereby was enormous.

We have performed the following works:

  • Wiring of the machines
  • Packing of all components
  • Piping
  • Central lubrication system
  • Survey of spare parts

Relocation of a complete can line with approx.. 90.000 cans/h from South France to Lorraine. The project contained the electrical and mechanical dismantling, the packing and the transportation as well as the overhaul and commissioning according to our own layout.